Progress Update
Installation of the mounting structures commenced in October 2020 and completed first week in November.
Installation of dc cables currently in progress with about 100 strings already completed.
Installation of pv modules commenced on Friday 13-11-2020.
No injuries registered so far and all COVID-19 protocols are strictly observed.
This project is scheduled for completion end of this year and with the current pace of work, this is highly attainable.